Value engineering (VE) is the systematic process of finding cost savings without sacrificing function, quality, or code compliance. On site civil projects, VE typically happens when the bid comes in over budget and the team needs to find savings quickly. The challenge is distinguishing between items that can be reduced without consequence and items where the "savings" will cost more in the long run through maintenance, repairs, or regulatory problems.
Where to Look First (High-Value VE Items)
1. Earthwork
Earthwork is often the largest single cost on a site development project. Small changes to the grading design can produce significant savings:
- Adjust pad elevations. Raising or lowering a building pad by 6 inches can swing thousands of cubic yards between cut and fill. If the site is importing fill, adjusting the pad to reduce the import volume saves $15 to $30 per CY.
- Reduce retaining wall heights. Adjusting grades to reduce a retaining wall from 8 feet to 6 feet can save 30 to 40 percent of the wall cost. Consider whether steeper slopes (within code limits) or grade adjustments to adjacent areas can reduce wall heights.
- Re-evaluate export. If the earthwork estimate shows a large export quantity, look for on-site areas where the excess material can be placed (landscape berms, fill behind walls, raising parking areas) rather than trucking it off-site.
2. Storm Drain and Utilities
- Reduce pipe sizes. If the drainage design used conservative assumptions (high runoff coefficients, short time of concentration), revisiting the calculations with more accurate inputs may allow smaller pipe sizes. Every size reduction (from 24-inch to 18-inch, for example) saves $30 to $60 per linear foot.
- Reduce pipe depths. Shallower pipes mean less excavation, less backfill, and less shoring. If the downstream connection allows a shallower alignment, take it.
- Eliminate unnecessary manholes. Manholes cost $5,000 to $10,000 each. If the pipe alignment has gentle curves that can be achieved with deflection at the joints (within the pipe manufacturer's limits), the intermediate manholes can be eliminated.
3. Pavement
- Separate truck and car areas. Design the truck loading areas and dock approaches with a heavier pavement section (6 inches AC over 12 inches AB) and the passenger car parking areas with a lighter section (3 inches AC over 6 inches AB). Do not build the entire lot to truck standards.
- Consider alternative materials. Concrete is more expensive than asphalt to install but lasts longer and requires less maintenance. For areas with light traffic and a long design life, concrete may have a lower life-cycle cost. Conversely, for areas that will be saw-cut frequently for utility access, asphalt is cheaper to repair.
Where Not to Cut
Stormwater Treatment BMPs
The stormwater treatment facility (bioretention, permeable pavement, etc.) is sized to meet regulatory requirements. Reducing its size means it does not meet the permit requirements, which means the project does not get a stormwater certification, which means the project does not get a certificate of occupancy. There is no savings here — only risk.
Fire Access
Fire lane widths, turning radii, and fire flow requirements are non-negotiable. Reducing a fire lane from 26 feet to 24 feet to save on paving saves a few thousand dollars and creates a fire code violation that will be caught during the fire marshal's final inspection. The correction at that point costs more than the original construction.
Accessible Routes and Parking
Accessibility requirements are federal and state law. There is no VE alternative to providing the required number of accessible parking spaces, the required route slopes, or the required curb ramp dimensions. Cutting accessibility items creates legal liability.
Compaction and Subgrade Preparation
Skipping the geotechnical testing or reducing the compaction effort saves a few thousand dollars during construction and risks hundreds of thousands in settlement repairs later. Subgrade preparation is the cheapest component of the pavement section to do right and the most expensive to fix when done wrong.
VE Process
- Identify the biggest cost items. Rank the civil cost estimate by line item. Earthwork, paving, storm drain, and retaining walls typically account for 60 to 80 percent of the civil budget. Focus VE efforts on these items.
- Separate code-mandated items from design choices. Items required by code (fire access width, ADA ramps, stormwater BMPs) cannot be reduced. Items that are design choices (pavement type, pipe material, wall type, slope ratio) can be reconsidered.
- Run the numbers. Every VE proposal should include the dollar savings, the functional impact, and any risk. "Switch from concrete to asphalt in the truck dock area" is not a VE proposal — it is a suggestion that will cause premature failure. "Switch from concrete to asphalt in the visitor parking area, saving $45,000, with no functional impact because the area sees only passenger car traffic" is a VE proposal.
- Get agency buy-in. If the VE change affects anything that the reviewing agency has already approved (fire lane layout, stormwater sizing, grading design), confirm with the agency that the change is acceptable before incorporating it. A VE change that triggers a new round of plan check is not a savings.
Have a project like this?
We can scope the civil engineering work and get you a proposal — usually within a week.